Bangladesh Cyclone Appeal Update
Introduction
The people of Bangladesh regularly have to deal with devastating natural hazards, but Cyclone Sidr caused untold damage in the region. All 13 Member Agencies ran programmes to help the people living in the 9 coastal districts most severely affected by the cyclone.
Programme Progress
84% (£5m) of DEC funds was distributed for the first allocation and in September 2008 a further £1 million was allocated to 5 of the DEC Agencies that were most on track with their first programmes.
After responding to the immediate emergency, Member Agencies focused on helping shattered communities rebuild their lives and livelihoods. The Bangladeshi Government assigned each agency an area in which to work, reducing the risk of overlap. With so many homes lost, providing shelter was crucial. DEC Agencies could not meet all the needs but each focused on helping those who were most vulnerable - the poorest, widows, the elderly and households headed by children. Some Member Agencies set out to support families without land, including fishing communities living precariously outside the coastal levies.
In addition to housing, support was directed towards rebuilding livelihoods through the provision of boats, seeds, tree saplings and other support including training. Member Agencies also rebuilt damaged schools and improved health through access to clean water by providing pond water filters, digging wells and hygiene education.
Headline Achievements After 9 Months’ Activity
DEC Agencies report that a total of 401,794 households, with an average of 5 people per household, have been assisted with these funds.
| Shelter & Construction | Water & Sanitation | Livelihoods |
|
|
|
| Health | Disaster Preparedness | Relief Items Distributed |
|
|
|
| Education & Training | ||
|
Challenges faced by the Member Agencies
The challenge presented by the requirement of the Bangladesh NGO Bureau to present all programme plans for approval before implementation resulted in significant delays for some agencies. This was compounded by the deliberations of the UN Shelter Cluster, which took 9 months to agree finally on a standard for the rebuilding of houses. Additional time was taken to secure land to build new homes for those who were previously classed as landless. The DEC took the view that it was better for the beneficiaries to have a quality programme than to rush expenditure. During this time, exchange rates moved adversely for sterling. All these factors resulted in fewer houses and boats being built with DEC funds than had been first planned. Member Agencies that decided to support families that did not own land faced delays in securing suitable plots. Despite this delay, some of the poorest and most vulnerable families now face a more secure future.
Review activity and lesson learning
A DEC Monitoring Mission identified that almost all Member Agencies appropriately used cash transfers and vegetable seed distribution to help with the early recovery, enabling communities to quickly re-establish gardens for the planting season. Three Member Agencies drew on lessons from previous disasters and targeted their shelter efforts on quality transitional materials to provide adequate protection against the impending monsoon. There was good evidence of involvement of beneficiaries in the disaster response with a high awareness of gender issues and the importance of respecting local customs and culture.
Many Member Agencies recognised their programmes were ambitious for the time allowed and had miscalculated the time it takes to get agreements on land and shelter design. Working with the landless was considered a positive intervention, despite the difficulties this presented. DEC Agencies worked closely with the Humanitarian Accountability Partnership to improve systems of working with communities. Through this they found new ways to advertise their programmes and set up feedback and complaints mechanisms.
Nine DEC Agencies have either undertaken or are in the process of commissioning evaluations of their programmes. Some of these will feature on the individual websites.
Conclusion
Cyclone Sidr caused huge damage to the coastal area of Bangladesh, with considerable loss of life. The affected area is not as prone to cyclones as other areas so many people were unprepared. DEC Agencies have a long standing presence in the country with sound relationships with partner agencies. This enabled many of them to quickly utilise resources to assist the early phase of the relief activities.
